Due to various State and Federal funding opportunities, the City of Coatesville has started a portion of the much needed road repairs throughout the City! Below is the schedule of repairs provided by our contractor, Construction Master Services. Please note that in some cases only portions of the streets will be repaired and all road repairs are weather dependent. Local residents will receive notification of road closures by the contractors in advance of the work.

  • September 1st:  Lemon Street
  • September 5th – September 13, in the following order:
    • Graham Avenue
    • 4th & Diamond
    • Lumber Street
    • 12th Avenue
    • 13th Street
    • Lemon Street

Also, PA American Water is completing paving work from 8/20 – 8-24 on Oak Street from 10th to 13th Ave.